1. Both sides asked the EU to revitalize the Mitrovica bridge and its surroundings, as per the recommendations of the technical assessment and based on the architectural design of 29 June 2015 agreed between the two sides.
2. On 15 October 2015 the contractor will close both sides of the bridge by fixed bridge barriers and construction site fence. The construction work on the bridge will be carried out by accessing the construction site through the southern acces road. The bridge will open for all traffic by summer/not later than end of June 2016.
3. In line with the same timetable, the municipality will revitalize its main street( King Peter Street) into a pedestrian zone. The street will open for pedestrians by summer/not later than end of June 2016.
4. The WG will regularly monitor and review together with both mayors the prevailing political and security conditions in municipalities during the revitalization process.
5. By 10 October 2015 the maps of administrative boundaries of cadastral areas in Suvi Do/Suhadoli and Kroi I Vitakut/Brdjani area will be solved through the Memorandum of Understanding on Municipal Development Plans, the Municipal Zoning Map and Detailed Regulaory Plan between relevant ministries and the two municipalities.